phase-1

  • 04

    Purchase of land and Registration

    WEEK 1 TO 4

  • 07

    Consulting Engineer / Architect, Design Drawing, Approval from authority

    WEEK 5 TO 12

phase-1

  • 02

    Time Schedule and Monthly Cash Outflow

    WEEK 10 TO 11

  • 02

    Contractor Selection

    WEEK 10 TO 11

phase-3
  • 01

    Borewell

    WEEK 12 TO 12

  • 03

    Excavation as per drawing

    WEEK 13 TO 15

  • 02

    Footing/Foundations*

    WEEK 16 TO 17

  • 02

    Pillars/Columns (Up to plinth level)

    WEEK 18 TO 19

  • 01

    Soil filling in trenches and compaction till ground leve

    WEEK 19 TO 19

  • 01

    Soil filling in trenches and compaction till ground level

    WEEK 19 TO 19

  • 02

    Plinth Construction*

    WEEK 20 TO 21

  • 02

    Pillars up to lintel level*

    WEEK 22 TO 23

  • 04

    Lintel*

    WEEK 24 TO 27

  • 02

    Pillars up to roof level*

    WEEK 26 TO 27

  • 02

    Soil filling and compaction till plinth level

    WEEK 26 TO 27

  • 05

    Roof Slab*

    WEEK 28 TO 32

phase-4-a
  • 07

    Brick Work & Curing

    WEEK 28 TO 34

  • 02

    Ducts for electrical wiring

    WEEK 35 TO 36

  • 01

    Frames for doors & windows

    WEEK 35 TO 35

  • 03

    Plastering & Curing

    WEEK 37 TO 39

  • 01

    Water Treatment, Heat Treatment

    WEEK 40 TO 40

phase-5
  • 04

    Flooring/Tiling

    WEEK 41 TO 44

  • 04

    Flooring/Tiling

    WEEK 41 TO 44

  • 03

    Water Supply, Sanitary & Plumbing

    WEEK 45 TO 47

  • 03

    Doors & Windows

    WEEK 45 TO 47

  • 04

    Painting

    WEEK 48 TO 51

  • 02

    Connections for electricity and drainage

    WEEK 50 TO 51

  • 02

    Inside furnishing

    WEEK 51 TO 52

phase-5
  • 01

    Completion/Occupancy Certificate

    WEEK 52 TO 52